PROJECT SCHEDULE

Pre-Project Activities (2023 – Early 2024)

  • Project Feasibility Studies: Conducted in Q3–Q4 2023.

  • Identified Gas Supplier & Commenced Due Diligence: Initiated in Q3 2023 and concluded by Q4 2023.

  • Partnership with Equipment Suppliers: Established in Q4 2023.

Project Development (2024 – 2025)

  • License to Establish (LTE) from NMDPRA: Secured in Q1 2024.

  • Execution of GSPA and LNG Offtake Agreements: Completed between Q1–Q2 2025.

  • Engineering Design (FEED & DED): Conducted from Q2 2024 to Q2 2026.

  • Project Funding: Secured between Q2 2025 and Q2 2026.

Procurement and Construction (2025 – 2026)

  • Procurement and Fabrication: Conducted from Q2 2025 to Q2 2026.

  • Civil Works, Construction, and Installations: Implemented from Q2 2025 to Q3 2026.

  • Commissioning and Training: Executed from Q3 2026 to Q4 2026.

Initial Operations (2026 – 2027)

  • Plant Start-Up and Reliability Run: Scheduled for Q4 2026 through Q2 2027.

Full Operations (2027)

  • Plant Handover and Full Operations Commencement: Planned for Q3 2027, marking the project milestone.

More about SAPELE LNG PROJECT

We deliver clean and cost-effective energy alternatives to Nigerian homes and businesses, to help our customers and the planet.

Company

Newsletter

Signup our newsletter to get update information, news & insight

10th Floor, Churchgate Tower, Plot 473 Constitution Avenue, Central Business District, FCT, Abuja.