Project Feasibility Studies: Conducted in Q3–Q4 2023.
Identified Gas Supplier & Commenced Due Diligence: Initiated in Q3 2023 and concluded by Q4 2023.
Partnership with Equipment Suppliers: Established in Q4 2023.
License to Establish (LTE) from NMDPRA: Secured in Q1 2024.
Execution of GSPA and LNG Offtake Agreements: Completed between Q1–Q2 2025.
Engineering Design (FEED & DED): Conducted from Q2 2024 to Q2 2026.
Project Funding: Secured between Q2 2025 and Q2 2026.
Procurement and Fabrication: Conducted from Q2 2025 to Q2 2026.
Civil Works, Construction, and Installations: Implemented from Q2 2025 to Q3 2026.
Commissioning and Training: Executed from Q3 2026 to Q4 2026.
Plant Start-Up and Reliability Run: Scheduled for Q4 2026 through Q2 2027.
Plant Handover and Full Operations Commencement: Planned for Q3 2027, marking the project milestone.